________ is the only constant
Change
When are change requests discussed and approved
?
- Develop epics process
- Create prioritized product backlog process
- Groom PPB
Scrum is a balance of _____ and ______
Flexibility & Stability
In relation to change, Scrum's flexibility comes from ______, while Stability comes from ___________
- being accepting of change at any time
- Keeping the sprint backlog unchanged during the sprint.
In case of an urgent change, what must be done?
Sprint must be terminated and the team meets to plan a new sprint
When does Change management in Scrum happen?
throughout.
When must user stories in the PPB be refined?
2-3 sprints in advance
the PPB review session is also called _______
groom PPB session
What duration is the groom PPB sessions time-boxed for?
These meetings are not time-boxed.